Choose the house

Number of sections and floors:

1 section; 24 –storey-building:

  • 1st floor – apartments and non-residential space (offices)
  • 2-24 floors – apartments.
Walls:
  • Exterior – prefabricated concrete panels 160 mm width with external insulation system on ventilated facades, loggias and balconies - insulated, plastered and painted.
  • Interior  – prefabricated ferroconcrete panels 160 mm width.
Partition walls:

Prefabricated ceramsite concrete panels – 92 mm.
Between office spaces and apartments the sound isolation system is designed according to calculations made.

Overlapping:

Prefabricated ferroconcrete panels 160 mm width. Flooring constructions – 50mm width.

Loft (attic):
cold
Roofing:
Roll coating.
Rainwater drainage:
interior.
Characteristics of fire prevention measures:
  • Stairs illumination – daylight, night time - electric;
  • Antismoke protection – according to the project;
  • Installed fire extinction pipes on every floor and in bathrooms in the apartments(FEP)
  • Fire extinction automatic system.
Number of elevators:
  • 2 elevators with 400 kg capacity;
  • 1elevator with capacity 1000 kg capacity ( for transporting firemen).
Floor height:
2,80m ( floor to floor).
Additional interior works:
  • entrance door to the apartment –  metal,shockproof;
  • Interior doors in the apartment – wooden frame MDF lined;
  • Windows and balcony doors – plastic with double glazing.
Interior finishing works in the apartments:

Rooms, living rooms , halls and hallways:

  • floor – oilcloth;
  • walls –  wallpaper;
  • ceiling –  paste whitewash.

Kitchen:

  • floor - oilcloth;
  • walls – washable wallpaper;
  • ceiling – paste whitewash.

Bathrooms (joined bathroom, lavatory,toilet):

  • floor – hydro isolation and ceramic tiling;
  • walls and ceiling – finishing interior works not made.
Bathroom equipment :

1-room apartments  - 1 steel bath,  1 wash basin, 1 toilet;

2-room apartments  - 1 steel bath, 2 wash basins, 1 toilet;

  • wash sinks in the kitchen are not installed;
  • stop bathroom armature and ball valves are installed
Towel dryers:
Electric, not installed. In the bathrooms and joined bathrooms an electric socket for the dryer is installed.
Type of oven:
Electric, not installed.
Wiring:
Made of copper wire with installation o sockets and switches.
Telephone cable, TV:
Wires (connection) performed to the boards on each floor. Connection with the apartment and the interior layout not made.
Heating system:

From heat-generating installation on the roof. Two- piped dual-zoned wiring:

  • first zone – 1 – 11 floors,
  • second zone – 12 – 24 floors.
The wires of heating system made to every apartment of polyethylene pipes in the floor structures.
Type of heating device:
steel radiators
Ventilation system:
Mandatory, in the kitchen and in bathrooms wall ventilators are installed.
Cold water supply:

Two-zoned.

Firstzone – 1 – 12 floors, with lower dilution of supply pipelines to the apartment risers located in each floor corridors of common use finishing at the 12th floor;
secondzone – 24 – 13 floors, with upper dilution of supply pipelines to the apartment risers located on each floor corridors of common use finishing at the 13th floor .

Hot water supply:

From heat-generating installation on the roof. Dual- zoned wiring:

Firstzone – 12 – 1 floors with upper dilution of pipelines to the apartment risers located in the corridor of common use on each floor and banding in the basement;
secondzone – 24 – 13 floors with upper dilution of pipelines to the apartment risers located in the corridor of common use in each floor and banding at the ceiling of the common hall on the 12th floor.

The wires of the systems of hot and cold water from the risers located in the corridors common use is made of polyethylene pipes in the floor structure.

 

Counters in each apartment:
  • electricity;
  • cold and hot water;
  • heating – located in the corridors of common use.
Finishing works on the corridors of common use:

Elevator hall, corridors of common use and stairs:

  • stairs floor –  concrete finish;
  • corridor of common use and elevator hall floor –  ceramic tiling;
  • elevator hall walls on the 1st floor –  ceramic tiling;
  • corridor of common use  and elevator hall walls at the typical floors – water resistant paint;
  • ceiling – paste whitewash;
  • entrance doors to the building – aluminum glazed;
  • interior doors –wooden;
  • windows – metal glazing.
Embellishment:
  • exterior lighting – according to the project;
  • roads, pavements, pedestrian paths – asphalt coating and FEM coating;
  • recreation areas: active rest, playground, temporary parking for vehicles.
Attention to the investors!
  1. It is forbidden to dismantle independently the constructive elements of the object, interior and exterior works and change the engineering communications.
  2. During the construction process the developer has the right to add/ change elements in the design and technological solutions of the residential building that do not degrade its consumer qualities and do not lead to violation of sanitary norms.
  1. The total area of the apartment is approximate; final calculations should be made according to the official data of technical inventory.