BUILDING “ASKANYA”(#16) RESIDENTIAL COMPLEX “PATRIOTYKA”, DARNYTSKIY DISTRICT       Kyiv, between B. Gmyri street and Kollektorna street  Choose the house

Number of sections and floors:
2 sections; 25 floors(25-storey building).
Walls:
  • exterior – prefabricated ferroconcrete blocks 160mm width with the insulation system on the external ventilated facades, in loggias and balconies  - insulation system, plaster and paint works are made.
  • interior – prefabricated ferroconcrete blocks 160 mm and 80 mm width.
  • Partition walls – artificial plaster panels 80 mm width
  • Between sections – prefabricated 3-layer panels 300 mm width.
Оverlapping:
Prefabricated ferroconcrete panels 160 mm width.
Loft(attic):
cold
Roof:

Roll coating.

Characteristics of fire prevention measures:
  • Lighting of stairs - daylight, at night time –  electric;
  • Antismoke protection – according to the project;
  • Installed fire extinction pipes on every floor and in bathrooms in the apartments(FEP)
  • Fire extinction automatic system
Number of elevators:

3 on each section, which are:

  • 2 elevators with  400 kg capacity ;
  • 1 elevator with 1000 kg capacity (also for firemen transportation).
Floor height:

2,80m ( floor to floor).

Additional interior works:
  • Entrance door to the apartment –  metal,shockproof;
  • Interior doors in the apartment – wooden frame MDF lined;
  • Windows and balcony doors – plastic with double glazing.
  • Glazing of loggias and balconies – 1 layer metal plastic glazing.
Interior finishing works in the apartments:

Rooms, living rooms , halls and hallways:

  • floor – oilcloth;
  • walls –  wallpaper;
  • ceiling –  paste whitewash.

Kitchen:

  • floor - oilcloth;
  • walls – washable wallpaper;
  • ceiling – paste whitewash.

Bathrooms (bathroom, toilet):

  • floor – hydro isolation and ceramic tiling;
  • walls and ceiling – finishing interior works not made.
Bathroom equipment :

1-room apartments  - 1 steel bath,  1 wash basin, 1 toilet;

2-room apartments  - 1 steel bath, 2 wash basins, 1 toilet;

3-room apartments – 1 steel bath, 2 wash basins, 2 toilets:

  • wash sinks in the kitchen are not installed;
  • stop bathroom armature and ball valves are installed
Towel dryers:

Electric, not installed. In the bathrooms and joined bathrooms an electric socket for the dryer is installed.

Type of oven:
Electric, not installed.
Wiring:
Made of copper wire with installation o sockets and switches.
Telephone cable, TV:
Wires (connection) performed to the boards on each floor. Connection with the apartment and the interior layout not made.
Heating system:

Two- piped dual-zoned wiring, for every apartment, with low wire connection:

  • first zone – 1 – 11 floors,
  • second zone – 12 – 25 floors.
The wires of heating system made to every apartment of polyethylene  pipes in the floor structures.
Type of heating device:
steel radiators
Ventilation system:

Mandatory,  in the kitchen and in bathrooms wall ventilators are installed.

Cold water supply:

2-zoned.

  •  First zone – 1- 12 floors inclusive (water supply in ascendant way).
  •  Second zone –25—13 floors inclusive (water supply in descendant way).
Supply pipelines are located under the ceiling of the corridor of common use on the 25th floor.
Hot water supply:

2-zoned:

    First zone – 12- 1 floors inclusive (water supply in descendant way).
Supply pipelines are located under the ceiling of the corridor common use on the 12th floor.

    Second zone –  25-13-floors inclusive  (water supply in descendant way).

Supply pipelines are located under the ceiling of the corridor of common use on the   25th floor.

Circulation pipelines of the second zone are located under the ceiling of the corridor of common use on the 12th floor.

Each apartment dilution of hot and cold water from pipelines, placed in cabinets corridors of common use, connection to places of bathroom equipment performed with polyethylene pipes in apartments` floor structures.

Installment and settlement of the Counters:
  • electricity –  each apartment;
  • cold and hot water – each apartment;
  • heating – located on the corridors of common use for every apartment.
Finishing works on the common halls:

Elevator hall, corridors  of common use and stairs:

  • stairs floor –  concrete finish;
  • corridor of common use and elevator hall floor –  ceramic tiling;
  • elevator hall walls on the 1st floor –  ceramic tiling;
  • corridor of common use and elevator hall walls at the typical floors – water resistant paint;
  • ceiling – paste whitewash;
  • entrance doors to the building – aluminum glazed;
  • interior doors –wooden;
  • windows –  wooden and metal glazing.
Embellishment:
  • exterior lighting – according to the project;
  • roads, pavements, pedestrian paths – asphalt coating and FEM coating;
  • recreation areas: active rest, playground, temporary parking for vehicles.
Attention to the investors!
  1. It is forbidden to dismantle independently the constructive elements of the object, interior and exterior works and change the engineering communications.
  2. During the construction process the developer has the right to add/ change elements in the design and technological solutions of the residential building that do not degrade its consumer qualities and do not lead to violation of sanitary norms.
  3. The total area of the apartment is approximate; final calculations should be made according to the official data of technical inventory.