NEWS FROM THE CONSTRUCTION SITES

 All news
23.10.2019
CONSTRUCTION OF THE BUILDING №27 AT R/C «ЕVRYКА»

Inside the residential building № 27 are being held interior works on partition walls and walls dividers. On 22.09.2019 wall and ceiling installation work is being carried out on both sections of the house.

Section №1 - Section 1 completes the 21st floor installation and begins the 22nd floor installation work.

Секція №2 - finishing the installation of the overlap of the 20-th floor.

The further construction will be faster and with increasing the volume of built objects.

Bank «АRCADA» is planning to post regularly the information about the construction of residential buildings.