31.01.2020
CONSTRUCTION STAGES OF THE RESIDENTIAL BUILDING №31 R/C «ЕVRYКА»
 
On 29.01.2020 in the building are developed the following works:
 
  Section 1:
- installation of ventilation units on the 5th floor and installation of beams for  installation of the stairs of the 5th
  floor;
- installation of formwork, installation of pipes for electrical distribution and concreting  of monolithic vertical      
  structures of the 5th floor and reinforcement;
- brick laying of walls of the 1st floor.
 
  Section 2:
- installation of reinforced concrete and monolithic structures of the 6th floor is completed;
- installation of formwork under the device of overlapping above the 6th floor;
 
Nowadays there are 32 constructors working on the site: installation professionals — 13, concrete workers — 6, electrician— 1, electric welder — 1, carpenters — 6, plaster professionals — 4,  crane operator— 1.
 
The subcontracting organization has all the necessary construction materials, production units and equipment as well as the necessary number of qualified staff.
 
Bank «АRCADA» plans to regularly the information about the construction progress of the residential complexes.
 
                   
         