13.03.2020
CONSTRUCTION STAGE IN THE RC “EVRYKA” BUILDING 27
 
On 12/03/2020 on the construction site of building 27 R/C «ЕVRYKA» the following is made:

Section 1
Installation of precast concrete structures of the house, installation of internal partitions, preparation and sealing of inter-panel seams, laying of air-ducted ventilation systems and installation of ventilation devices are completed.

Works are being carried out on the installation of insulation and screed over the apartments of the 24th floor and the machine room of elevators, a metal railing on the roof, a pre-plastering complex of laying cables for the power supply of apartments and public places. 
 
Section 2
Installation of precast concrete structures of the house and installation of ventilation equipment is completed.

At the stage of completion of work on the installation of internal partitions, sealing of inter-panel seams, pre-plastering complex laying of cables for power supply of apartments and places of common use, metal fencing on the roof.

Work is started and actively carried out on the installation of roof insulation, followed by the implementation of screeds and rolled carpet to prevent the fall of atmospheric precipitation inside the house.

Today, 8 workers and one tower crane operator work on the construction of the residential building # 27.

The contracting organization is provided with all the necessary building materials, production facilities and mechanisms, as well as a sufficient number of skilled workers.

     
   

 


 
 
 

 
 

 